True or False: If “develop online modules” needs to begin before “review online modules” can begin, that is
called a start to start relationship.
A. True
B. False
Đáp án:
Option A:
Option B:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
When you schedule work in a specific order because it cannot be completed any other way, what is the type
of dependency used?
A. Discretionary
B. Internal
C. Mandatory
D. External
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
As you plan your project, the sponsor informed you that all team members will be assigned to your project for
at most 50% of their available time. This is an example of:
A. Poor planning.
B. Wishful thinking.
C. A project demand.
D. A constraint.
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Your stakeholder register should not contain:
A. Identification information
B. Assessment information
C. Stakeholder classification
D. Scope information
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
True or False: Your role as the project manager during quality assurance is to implement the quality
management plan using the appropriate tools and techniques, in order to ensure that work is being performed
according to required quality standards.
A. False
B. True
Đáp án:
Option A:
Option B:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
True or False: The critical path is the shortest path through the network and represents the work that can be
delayed without delaying the end of the project.
A. False
B. True
Đáp án:
Option A:
Option B:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
When you have good historical information which can be used in a reliable formula or model, you will probably
use:
A. Parametric estimating
B. Exact estimating
C. Analogous estimating
D. Bottoms up estimating
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which of the following is NOT the output of Plan Scope Management process? (Choose 2 answers)
A. Scope Management Plan
B. Requirement Management Plan
C. Quality Management Plan
D. Time Management Plan
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
The WBS is used to derive all but one of the following:
A. The project schedule baseline
B. The business need for the project
C. The project cost performance baseline
D. The activity list
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which of the following best describes the project manager’s role as an integrator?
A. Help team members become familiar with the project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
True or False: Effective project communication management creates a bridge between stakeholders based on
a shared understanding of the project and the ongoing sharing of information needed for its success.
A. True
B. False
Đáp án:
Option A:
Option B:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which process group focuses on completing the requirements of the project?
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
E. Closing
Đáp án:
Option A:
Option B:
Option C:
Option D:
Option E:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
When you and your team know that a positive risk has a high likelihood of occurring and it will be very
beneficial if it does:
A. You should not document the risk as it will not impact badly to your project.
B. You should develop a contingency plan and ask your management for contingency reserve.
C. You should transfer the risk to the vendor owned by your friend so he/she can earn the benefit.
D. You should develop the mitigation plan to reduce the probability of the risk happen.
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
The network diagram is the best tool for demonstrating:
A. Schedule performance over time
B. Schedule variances
C. Resource requirements
D. The sequence of project activities