PMG201c_RESP24_534444


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3.
Using the following project status chart to calculate project current PV:

Đáp án:

  • Option A: PV = $3,000
  • Option B: PV = $2,500
  • Option C: PV = $3,250
  • Option D: PV = $2,200
  • Option E: PV = $2,650
  • Option F: PV = $3,100
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

You have finished planning and have begun executing the project when the client asks if you would add some
important features to the product of the project. How are the triple constraints affected?
A. Time and cost may both be affected
B. Scope and quality would be affected but not cost
C. Cost must remain constant because resources are limited
D. Adding features will require additional cost but not time

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

Which of the following is NOT the disadvantages of top-down estimating?
A. Costly to create
B. Less accurate
C. Requires considerable experience to do well
D. Does not take into account the differences between projects

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

As discussed in the Project Management course, The PMBOK® Guide describes 10 Project Management
Knowledge Areas. Identify 3 out of the 10:
A. Stakeholder, Communication, Human Resource
B. Stakeholder, Vendor, Customer
C. Risk, Human Resource, Vendor
D. Procurement, Communication, Customer

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

True or False: Authority means you have the right to apply resources, make decisions and give approvals.
A. False
B. True

Đáp án:

  • Option A:
  • Option B:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

True or False: The worst organization to use to run a project will always be the functional organization.
A. True
B. False

Đáp án:

  • Option A:
  • Option B:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

True or False: Project Human Resource Management includes the processes that define the tasks and assign
them to suitable resources, and motivate project team to complete the tasks.
A. False
B. True

Đáp án:

  • Option A:
  • Option B:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

Operational work is different from project work in that operational work is:
A. Unique
B. Temporary
C. Ongoing and repetitive
D. A part of every project activity

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

True or False: The Backward Pass is used through the activities to determine the critical path & available float of
the project.
A. True
B. False

Đáp án:

  • Option A:
  • Option B:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

Which one of these most correctly defines management reserve?
A. Per our lesson, management reserve and contingency are exactly the same.
B. Management reserve is not tied to specific work packages it is for the entire project.
C. Management reserve is tied to specific work packages.
D. Management reserve is tied to a specific milestone or event.

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada:


Câu hỏi:

Dịch từ hình

(Choose 1 answer)

Which statement is not correct?
A. Project scope is the work that needs to be accomplished to deliver a product, service, or result.
B. Product scope completion is measured against the product requirement.
C. Project scope completion is measured against the project management plan and specially the project
scope statement, the work breakdown structure (WBS), and the WBS dictionary.
D. Product scope is the work that needs to be accomplished to complete a project

Đáp án:

  • Option A:
  • Option B:
  • Option C:
  • Option D:
0 voters

Hashtags: Đề thi mới PMG201
Comment tại sao bạn lại chọn như vậy bên dưới nhé :tada: