You have a project to build a new fence. The fence will form a square. Each side is to take one day to build, and $1,000 has been budgeted per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using the following project status chart to calculate project current PV:
Đáp án:
Option A: PV = $3,000
Option B: PV = $2,500
Option C: PV = $3,250
Option D: PV = $2,200
Option E: PV = $2,650
Option F: PV = $3,100
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
You have finished planning and have begun executing the project when the client asks if you would add some
important features to the product of the project. How are the triple constraints affected?
A. Time and cost may both be affected
B. Scope and quality would be affected but not cost
C. Cost must remain constant because resources are limited
D. Adding features will require additional cost but not time
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which of the following is NOT the disadvantages of top-down estimating?
A. Costly to create
B. Less accurate
C. Requires considerable experience to do well
D. Does not take into account the differences between projects
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
As discussed in the Project Management course, The PMBOK® Guide describes 10 Project Management
Knowledge Areas. Identify 3 out of the 10:
A. Stakeholder, Communication, Human Resource
B. Stakeholder, Vendor, Customer
C. Risk, Human Resource, Vendor
D. Procurement, Communication, Customer
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
True or False: Project Human Resource Management includes the processes that define the tasks and assign
them to suitable resources, and motivate project team to complete the tasks.
A. False
B. True
Đáp án:
Option A:
Option B:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Operational work is different from project work in that operational work is:
A. Unique
B. Temporary
C. Ongoing and repetitive
D. A part of every project activity
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which one of these most correctly defines management reserve?
A. Per our lesson, management reserve and contingency are exactly the same.
B. Management reserve is not tied to specific work packages it is for the entire project.
C. Management reserve is tied to specific work packages.
D. Management reserve is tied to a specific milestone or event.
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters
Hashtags:Đề thi mớiPMG201 Comment tại sao bạn lại chọn như vậy bên dưới nhé
Which statement is not correct?
A. Project scope is the work that needs to be accomplished to deliver a product, service, or result.
B. Product scope completion is measured against the product requirement.
C. Project scope completion is measured against the project management plan and specially the project
scope statement, the work breakdown structure (WBS), and the WBS dictionary.
D. Product scope is the work that needs to be accomplished to complete a project
Đáp án:
Option A:
Option B:
Option C:
Option D:
0voters